Step by step, we are bringing life back to the Transfiguration Cathedral.
The roof, facade, altars, walls, the rotunda — everything that was destroyed now stands again.
Work continues every day. We do not stop.
What has already been done:
- — more than 1300 m³ of debris cleared
- — damaged walls, floors and the rotunda dismantled
- — new exterior and interior walls built
- — the roof, covering and trusses fully restored
- — the right altar fully rebuilt up to the plastering stage
- — the left altar fully restored
- — walls and ceiling of the main altar restored
- — windows and doors installed
- — the entrance to the church, staircases, partitions and floors restored
- — a new ceiling built
- — rotunda columns restored, metal structures installed
- — reinforced concrete belt and lintels arranged
- — facade works completed
Currently in progress:
- — restoration of the rotunda
- — restoration of the pendentives and arches of the central dome
- — finishing works in certain parts of the church
What lies ahead:
- — full restoration of the interior, flooring and decorative elements
- — completion of the ceiling
- — work on interior finishing and sacred details
Together we are capable of anything!